|
Images
Audio Clips
Video Clips
Movies
Documents
|
 |

FINAL PREPARATIONS: 1968
Lunar Receiving Laboratory
Construction of the lunar receiving laboratory was virtually complete by
the middle of 1967; Hess held a press conference to open the new
facility on June 29.18 For the rest of
the year and much of 1968, NASA and Brown & Root-Northrop, support
contractor responsible for operating the laboratory, were occupied with
installation and testing of the specialized equipment required for
quarantine testing and sample handling. Brown & Root-Northrop set up
training programs for the technicians who would do much of the work in
the laboratory. In April 1968, to assure coordination of effort between
quarantine studies and scientific investigations, the two MSC
directorates principally involved - medical research and operations and
science and applications - began holding monthly meetings on the status
and problems of the receiving laboratory.19 MSC officials planned an operational readiness
inspection for the last quarter of 1968, and contemplated partial and
complete simulations as soon as they could begin, to exercise the
laboratory's functions and uncover flaws in equipment and procedures.20
As could be expected for a facility of such complexity, many technical
problems arose in the lunar receiving laboratory during the installation
and testing of its equipment. Both in the sample-handling area and in
the biological laboratories, difficulties slowed progress until late
summer.21 By mid- September, however,
problems with autoclaves (pressure vessels for sterilizing items to be
transferred out of the biological containment area) were the only
serious concern. Laboratory managers prepared and sent to the MSC
director a request to appoint an Operational Readiness Inspection Board
for the receiving laboratory.22
While awaiting completion of the laboratory, scientists on the
preliminary examination team and the lunar sample analysis planning team
were busy defining their procedures and preparing for simulations.23 Both teams met at Houston frequently
during 1968 to discuss issues of importance in operation of the
laboratory and to maintain liaison with the principal investigators. For
the outside members of these teams, many of whom were university
researchers, preparations for the laboratory work to follow the first
lunar landing entailed a considerable sacrifice of time from their
normal duties.24 Simulations would
require from 10 to 30 consecutive days of work in the laboratory.
Late in October the science teams gathered in Houston to conduct a
training session and simulation of operations in the sample-receiving
and -processing sections of the receiving laboratory.25 The 10-day exercise uncovered 82 major and minor
faults in equipment. A substantial number of these impaired effective
operation of the vacuum system in which the sample return containers
were opened. The vacuum chamber, like most of the other cabinets that
comprised the primary biological barrier, was a "glove box,"
designed so that various tools, stored inside, could be manually
manipulated through a pair of impermeable gloves built into the chamber
wall. The gloves had to withstand a pressure difference of around 100
kilopascals (15 pounds per square inch - a high vacuum inside and normal
atmospheric pressure outside); consequently they were stiff, making it
difficult for the operator to use the small hand tools with any
dexterity and sensitivity. The simulation also revealed that the viewing
ports left blind spots for the operator in some corners of the chamber.
These and other problems necessitated more than 80 major and minor
changes to the system and procedures before a full mission simulation
could be conducted some time in early 1969.26 MSC established a configuration control board
for the receiving laboratory to pass on proposed changes and keep
nonessential ones from proliferating.27
By October 1968 sufficient progress had been made to conduct an
operational readiness inspection - a mandatory procedure for all MSC
facilities. MSC Director Robert R. Gilruth appointed a 10-person
committee to review the facilities, staffing, and operational plans.28 After an initial meeting in early
November and a complete briefing two weeks later, committee members
spent a month scrutinizing physical facilities, staffing and personnel
training, and operational procedures.29
The committee's recommendations, submitted in mid-December, included 72
mandatory and 91 desirable changes necessary to render the laboratory
acceptable for operation.30
Preparations for a 30-day simulation of receiving laboratory operations,
scheduled for March and April, occupied most of the early months of
1969. In the interim between the operational readiness inspection and
the simulation, laboratory staff and contractor employees worked to iron
out the remaining problems.
18. MSC, "Lunar Receiving
Laboratory Briefing," transcript of presentation, June 29, 1967;
MSC, "Annual Report for Calendar Year 1967, The Directorate of
Medical Research and Operations, Manned Spacecraft Center," n.d.
[Dec. 1967].
19. Edgar M. Cortright to Gilruth, Mar.
27, 1968; Hess to Dir., Medical Research & Operations,
"Initiation of monthly review meetings on LRL," Mar. 29, 1968.
20. Hess to multiple addressees,
"Preliminary Examination Team Simulation Tests and Full Scale LRL
Simulation," Aug. 20, 1968.
21. Gilruth to Charles W. Mathews, May
17, 1968; Minutes, Monthly LRL Reviews, June 10, July 1, Aug. 12, 1968.
22. MSC, "Minutes of Monthly LRL
Review," Sept. 16, 1968; John E. Pickering, "Trip Report [to
LRL monthly manager's review]," Sept. 18, 1968.
23. P. R. Bell to Martin Favero, June
18, 1968; "[Minutes,] Lunar Science Analysis Planning Team, July 26
[1968]"; Hess to multiple addressees, "Preliminary Examination
Team Simulation Tests and Full Scale LRL Simulation," Aug. 20,
1968.
24. Gilruth to Edward H. Levi (Univ. of
Chicago), Feb. 25, 1969.
25. Bell to Members of Preliminary
Examination Team, "The Preliminary Examination Team simulation and
training session, October 22 through November 1, 1968," Oct. 16,
1968.
26. Test dir., vacuum laboratory,
"Report on PET Simulation, October 25-30, 1968," Oct. 31,
1968; Bell to Dir., Science and Applications, "LRL Equipment and
System Problems," Nov. 7, 1968.
27. Hess to L. R. Scherer, "Changes
in the Lunar Receiving Laboratory," Dec. 6, 1968; Hess to LRL
Staff, "Configuration Control Board (CCB)," Dec. 6, 1968.
28. Gilruth to multiple addressees,
"Operational Readiness Inspection of the Lunar Receiving
Laboratory," Oct. 21, 1968.
29. Peter J. Armitage to multiple
addressees: "Minutes of the First ORI Committee Meeting for the
Lunar Receiving Laboratory," Nov. 5, 1968; "Minutes of the
Second ORI Committee Meeting for the Lunar Receiving Laboratory,"
Nov. 22, 1968; "Minutes of the Third ORI Committee Meeting for the
Lunar Receiving Laboratory," Dec. 4, 1968; "Minutes of the
Fourth ORI Committee Meeting for the Lunar Receiving Laboratory,"
Dec. 4, 1968; "Status of the Operational Readiness Inspection on
the Lunar Receiving Laboratory and the Recovery Quarantine
Equipment," Dec. 19, 1968; "Minutes of the Fifth ORI Committee
Meeting for the Lunar Receiving Laboratory," Dec. 23, 1968.
30. Armitage, "Final Report,
Operational Readiness Inspection of the Lunar Receiving Laboratory and
Recovery Quarantine Equipment," May 7, 1969.
|