|
Images
Audio Clips
Video Clips
Movies
Documents
|
 |

FINAL PREPARATIONS: 1968
Final Simulations and Certification
The successful flight of Apollo 8 into lunar orbit during
the Christmas season of 1968 emphasized the fact that a lunar landing
was fast approaching and that preparations for back-contamination
control were becoming critical. Headquarters began to take a more active
interest in the receiving laboratory and related operations as 1969
began. Apollo program director Sam Phillips came to Houston in early
February for a thorough review of containment from splashdown to release
from quarantine.45 Ten days later
George Mueller, whose Office of Manned Space Flight had just been given
full responsibility within NASA for back-contamination control, brought
a group of advisers from the regulatory agencies to scrutinize Houston's
preparations.46 These advisers found
the receiving lab far from ready to handle a mission: equipment
problems, a shortage of technicians, incompletely trained personnel, and
deficient protocols for biological testing all required work.47
These and other deficiencies were expected to surface during a
month-long dress rehearsal of laboratory operations scheduled to start
March 3. This exercise could not exactly simulate every detail of
operations because of equipment limitations, but it would come as close
as possible. During the second week a simulation of recovery operations
would be run in connection with the flight of Apollo 9, to evaluate the
transfer of astronauts from the recovery ship to the mobile quarantine
facility and then to the crew reception area of the lunar receiving
laboratory.48
Expectations were borne out by the results of the simulation. Scores of
faults, most of them minor but some of them critical, emerged in both
equipment and procedures.49 Among the
more serious problems was contamination of the first work station - the
vacuum chamber in which the lunar sample containers were opened. Somehow
minute traces of organic matter had found their way into the system,
threatening to vitiate the search for indigenous organic material in the
samples. Worse yet, the level of contamination was not constant, so the
investigators could not correct their findings for it. When it appeared
that the contamination came from the vacuum pumping system,
investigators began to consider alternatives to opening the sample
containers under vacuum to keep the lunar material in pristine
condition. The best choice seemed to be to fill the chamber with a gas
(sterile nitrogen) that would not interfere with subsequent analyses.50
The receiving laboratory staff continued to work on the many details of
laboratory operation throughout the spring. Progress continued toward
certification of the quarantine facilities and back-contamination
procedures.51 By the time the
interagency committee met on June 5, MSC had completed action on most of
the outstanding questions and the committee granted certification of the
lunar receiving laboratory as a biological containment facility.52 The launch of Apollo 11 was only five weeks
away when another mission simulation got under way in the laboratory,
with only minor technical problems remaining to be worked out.53
Considering the technical sophistication of the receiving laboratory and
the rigorous procedures for handling the lunar samples, it is hardly
surprising that problems persisted as long as they did. Management
arrangements contributed as well; the outside scientists who were
intimately involved in examination and distribution of the samples could
not spend full time at MSC, making continuity of activity more
difficult. Wilmot Hess was sensitive to the need for close cooperation
between MSC and the outside scientific community, and the relationships
established in the two years before the first landing went a long way
toward alleviating the problem.
Quarantine and back-contamination control added to the overall
complexity. Without a doubt, most engineers and lunar scientists at MSC
took the back-contamination problem much less seriously than did the
interagency committee - which, unfortunately for the engineers, had the
authority to impose its requirements on the program. The reemergence in
early 1969 of concern with back-contamination during recovery operations
can be attributed to the committee's perception that MSC was not
cooperating to solve the problem because the engineers considered it
unimportant.54 In the end, the
committee yielded at least as much as the engineers on the question of
biological containment, but it required considerable effort and tactful
interaction with the committee to produce that result.
The start of operations in the receiving laboratory coincided with a
period of retrenchment in NASA, and technical difficulties were
compounded by personnel problems. Rising budget deficits in the last two
years of Lyndon Johnson's administration had alarmed Congress and put a
real squeeze on federal programs, not excepting NASA's. Apollo suffered
less than other programs,55 but it was
not completely immune to economy measures. Ever since authorization
hearings began in early 1968 the field centers had been under pressure
to reduce expenditures and cut staff.56
MSC's inability to add professional staff in the receiving laboratory
affected more than just the science. Four months before Apollo 11 flew,
the Office of Manned Space Flight's operations forecast for 1969 showed
lunar landing missions being launched at two- to three-month intervals
after the first. Gilruth took exception, however, advising Headquarters
that, with its current complement of professionals, the lunar receiving
laboratory could support a lunar mission only once every four months and
that only if all went well during each quarantine period.57 The laboratory had enough professional staff
to operate only two fully productive shifts a day; a third "holding
shift" was manned principally by technicians, who maintained the
laboratory but did not continue processing the samples.58
Nonetheless, on June 4, 1969, mission operating conditions were
established in the laboratory,59 and a
Task Group was formed to direct operations during the Apollo 11
mission.60 With the launch date for
Apollo 11 inexorably approaching, the laboratory staff continued to
refine sample-handling procedures and work on the last remaining
technical problems.
45. Phillips to Gilruth, "Lunar
Receiving Laboratory Readiness Review," Jan. 16, 1969; Gilruth to
Phillips, Jan. 29, 1969, with tentative agenda for proposed review.
46. Mueller to Gilruth, Jan. 13, 1969;
Gilruth to Mueller, Feb. 8, 1969.
47. A. B. Park to Pickering, Mar. 7,
1969, with encl., "Report by U.S. Department of Agriculture Team on
Lunar Receiving Laboratory Evaluation for Quarantine Requirements,"
n.d.; Howard H. Eckels to Pickering, Mar. 11, 1969, with encl.,
"Department of Interior Observations on the Lunar Receiving
Laboratory Procedures Relative to Invertebrate and Fish Species,
February 12, 13, and 14, 1969"; idem, Feb. 27, 1969, with encl.,
Kenneth E. Wolf to Eckles, "Technical Review of Lunar Receiving
Laboratory," Feb. 25, 1969; Pickering to Dir., Apollo Program,
"LRL Bioprotocol Readiness Review and Certification
Procedures," Feb. 24, 1969.
48. MSC, "Lunar Receiving
Laboratory Simulation Plan, March 3-April 16, 1969," n.d., pp. 1-2.
49. Rudy Trabanino to LTD's [Laboratory
Test Directors], "Debriefing of Laboratory Personnel," Mar.
16, 1969; D. White to LTD's, "Critique of 3-13 March Simulation in
Vacuum Laboratory - Shift I," Mar. 16, 1969; T. McPherson to LTD's,
"Vacuum Laboratory Critique - Second Shift," Mar. 16, 1969;
Trabanino to LTD's, "Critical Vacuum Laboratory Problems,"
Mar. 21, 1969; O. A. Schaeffer and J. G. Funkhauser to Bryan Erb,
"Leak Checking of RCL Containers with Gas Analysis System,"
Mar. 24, 1969; Bell to Deputy Mgr., LRL, "Problems Identified in
February and March LRL simulations," Mar. 27, 1969; H. C. Sweet and
Charles H. Walkinsbau, Jr., "Summary of Simulation of Botanical
Protocol - March 1969," n.d. [Mar. 1969]; "Minutes,
Interagency Committee on Back Contamination, 28-29 March 1969-Manned
Spacecraft Center - Houston, Texas," Mar. 29, 1969; Trabanino,
"Critical Vacuum Laboratory Problems," Apr. 3, 1969.
50. Hess to Bell, "Organic
Contamination of F201," Apr. 8, 1969.
51. Johnston to multiple addressees,
"Action items from Interagency Committee on Back Contamination
(ICBC) Meeting," May 5, 1969; Gilruth to multiple addressees,
"Establishment of Apollo Back Contamination Control Panel,"
May 8, 1969; Johnston to Chief, Crew Systems Div., and Chief, Flight
Crew Support Div., "Lunar Module Back Contamination
Simulation," May 12, 1969; Johnston to Col. John E. Pickering, May
14, 1969; Johnston to multiple addressees, "Action Items from
Interagency Committee on Back Contamination (ICBC) Meeting, May 2,
1969," May 15, 1969; idem, "ICBC Telephone Conference Summary
and Action Items," May 21, 1969; MSC, "Back Contamination
Mission Rules (Recovery to Receiving Lab)," MSC 00005, May 21,
1969; Low to multiple addressees, "Back Contamination
Procedures," May 20, 1969; Robert E. Smylie to Mgr., Apollo
Spacecraft Program, "Back Contamination Procedures," May 22,
1969; Johnston to multiple addressees, "Apollo Back Contamination
Simulation Meeting Summary," May 23, 1969; idem, "Back
Contamination Action Items," May 28, 1969.
52. Mueller to Administrator,
"Manned Space Flight Weekly Report," June 9, 1969.
53. Johnston to multiple addressees,
"Apollo Back Contamination Simulation Meeting Summary," May
23, 1969.
54. Sencer to Paine, Apr. 7, 1969.
55. W. David Compton and Charles D.
Benson, Living and Working in Space: A History of Skylab,
NASA SP-4208 (Washington, 1983) , pp. 99-102.
56. Hess to MSC Dir., "Summary OSSA
Senior Council Meeting," Apr. 30, 1968; Hess to John E. Naugle,
"Staffing of the LRL," June 6, 1968; Naugle to Hess, same
sub., July 9, 1968; M. L. Raines to Assoc. Dir., "Systems and
Support Contractor Reduction," July 12, 1968; MSC, "Minutes of
Monthly LRL Review, September 16, 1968"; Earle B. Young to LRL ORI
Committee, "Proposed LRL Staffing," Nov. 26, 1968; P. R. Bell
to Dir., Science and Applications, "Staffing Plan for the Lunar and
Receiving Laboratory," Jan. 17, 1969; Wesley L. Hjornevik to Lt.
Gen. Frank A. Bogart, "Lunar Receiving Laboratory Staffing,"
Jan.27, 1969; MSC, "LRL Staffing Plan Status, April 8, 1969,
Science & Applications Directorate and Medical Research &
Operations Directorate."
57. John D. Stevenson, TWX to multiple
addressees, "MSF mission operations forecast for January
1969," Jan. 3, 1969; Gilruth to Stevenson, "Ability to support
launch schedule for CY 1969," Mar. 4, 1969.
58. Bell to Dir., Science and
Applications, "Staffing plan for the Lunar and Receiving
Laboratory," Jan. 17, 1969.
59. W. W. Kemmerer, Jr., to all LRL
personnel, "Initiation of mission operating conditions for the
Sample Laboratory secondary biological barrier," June 3, 1969.
60. Johnston to all NASA LRL personnel,
"Lunar Receiving Laboratory Apollo 11 Task Group," June 4,
1969.
|